Green Court Bucharest - building B |
Construction works to building B of the office complex Green
Court Bucharest (2-4 Gara Herastrau St.) have reached the 10
th floor
of the total 13 floors. OCTAGON team have worked at a very fast pace and
|
Green Court Bucharest - building B |
|
have
managed to build the 10 floors of the superstructure in only 4 months.
Right now
OCTAGON is performing
concrete structure works:
encasing,
concrete reinforcement and
metal structure works. “Concrete structure
works
have reached the 10
th floor and metal structure works have
reached the 6
th floor.”
said Mihaela
Moraru- CTCC engineer.
|
Green Court Bucharest - building B |
|
Building B is the second on the three buildings of the
complex. OCTAGON has also delivered building A, where the company performed
infrastructure works (diaphragm walls D 600; crown beams; anchors), concrete
structure works and superstructure works.
Building A has 15 floors.
|
Green Court Bucharest - building B |
|
OCTAGON
contract for this building has been supplemented with exterior works:
construction of access stairs, access ramps for people with disabilities and
protection fences.
|
Green Court Bucharest - building B |
|
Green Court Bucharest will have a total leasable area of
52,000 sqm. The complex, developed by Sweedish company Skanska will be LEED
Gold certified.