OCTAGON construction works have reached the 10th floor of Green Court Bucharest- building B




Green Court Bucharest - building B
Construction works to building B of the office complex Green Court Bucharest (2-4 Gara Herastrau St.) have reached the 10th floor of the total 13 floors. OCTAGON team have worked at a very fast pace and
Green Court Bucharest - building B
have managed to build the 10 floors of the superstructure in only 4 months.

Right now OCTAGON is performing concrete structure works: encasing, concrete reinforcement and metal structure works. “Concrete structure works have reached the 10th floor and metal structure works have reached the 6th floor.”  said Mihaela Moraru- CTCC engineer.
Green Court Bucharest - building B


Building B is the second on the three buildings of the complex. OCTAGON has also delivered building A, where the company performed infrastructure works (diaphragm walls D 600; crown beams; anchors), concrete structure works and superstructure works.
Building A has 15 floors.
Green Court Bucharest - building B


OCTAGON contract for this building has been supplemented with exterior works: construction of access stairs, access ramps for people with disabilities and protection fences.
Green Court Bucharest - building B

Green Court Bucharest will have a total leasable area of 52,000 sqm. The complex, developed by Sweedish company Skanska will be LEED Gold certified.